After the Report
Unsatisfactory EICR: What a Landlord Must Do Within 28 Days
If your EICR is unsatisfactory, you must have the remedial work or further investigation completed within 28 days (or any shorter period the report states) and then give written confirmation to your tenants and, on request, the council within 28 days. An unsatisfactory result does not mean the property needs a rewire or a new consumer unit: it means the report lists at least one observation that has to be dealt with. This guide explains what makes a report unsatisfactory, how the 28-day clock runs, what the written confirmation must say and what happens if you cannot meet the deadline. The duties come from the 2020 Regulations explained.
Have your postcode, the number of bedrooms and consumer units, and your current report's next-inspection date ready.
- NICEIC Approved Contractor since 2021
- Price confirmed before we attend
- Phone line open 24/7
What Makes a Report Unsatisfactory
A report is unsatisfactory when any one of its observations is coded C1, C2 or FI. C1 means danger is present and there is a risk of injury now. C2 means the item is potentially dangerous. FI means the inspector could not reach a conclusion without further investigation, usually because something could not be seen or tested on the day. Any one of those three codes makes the overall assessment unsatisfactory.
A C3 means an improvement is recommended. A report whose only observations are C3s is satisfactory, so a C3 alone does not fail the report and does not start the 28-day clock, though acting on it is often sensible.
The inspector records the overall result in the assessment box on the front of the report, and lists each observation with its code and the location in the schedule of observations. If a C1 is found, the inspector will tell you on the day: switch off the affected circuit at the consumer unit if it is safe to do so and call a qualified electrician; in an emergency call 999. Exactly what the inspection covers is set out in what is checked and what is not.
Your 28-Day Clock
The inspection that starts all of this is part of our landlord electrical safety certificates service.
Read the observations and the period stated
go through the schedule of observations, note every C1, C2 and FI, and check whether the report sets a shorter period than 28 days for any of them. The clock starts on the date of the report.
Arrange a qualified person
have the remedial work, or the further investigation for an FI, carried out by a qualified and competent person within the period. The business can quote separately for the remedial work; it is not part of the inspection.
Obtain written confirmation
when the work is done, get written confirmation from the person who did it that the work has been carried out and the installation meets the standards, or that further work is still needed.
Send it within 28 days of completion
give a copy of that confirmation to every tenant and, where the council asked for it, to the council, within 28 days of the work being completed. Keep proof of sending.
Written Confirmation: What It Must Say
The written confirmation must come from a qualified and competent person: the electrician who carried out the remedial work or the further investigation. It must say either that the work has been carried out and the electrical safety standards are now met, or that further investigation or remedial work is still required, in which case a new period runs for that further work.
In practice the confirmation is usually a Minor Electrical Installation Works Certificate or an Electrical Installation Certificate for the work, together with a short letter or email referring to the original EICR and the observations it covered. Ask for the observation numbers to be listed so that anyone reading the two documents together can see that each item has been closed. Keep the confirmation with the EICR, hand both to the electrician at the next inspection, and keep your own copy for the whole period the regulations require.
If You Cannot Meet the Deadline
If the work cannot be completed within the period, the council has powers to act. It can serve a remedial notice giving you 28 days to comply, take urgent remedial action itself where a C1 is involved, recover its costs, and impose a civil penalty of up to thirty thousand pounds per breach. A landlord is not in breach, though, if they can show that they took all reasonable steps to comply: for example that the work was booked promptly, that the tenant would not allow access, or that a part was on order. Keep dated evidence of each step. The council powers are explained in the 2020 Regulations explained; for advice on your own position, speak to the council's private sector housing team.
Related Guides
Licensing by Borough
Which London boroughs run additional and selective licensing, with scheme dates, and what every licence adds to the landlord's national five-year EICR duty.
Tenant Refuses Access
What a landlord must do when a tenant will not allow access for an EICR: reasonable notice, the all reasonable steps defence, and what councils accept.
Agents and the EICR
Who is responsible for the EICR when a letting agent manages the property: the landlord's legal duty, the agent's contractual role and what to file.
Landlord electrical safety certificates
Arrange a Re-Inspection
If you want an independent re-inspection once the remedial work is done, or a fresh EICR for a property whose report has lapsed, call 020 3740 6785. All Service 4 U's phone line is open 24 hours a day, seven days a week; your fixed price is confirmed before we attend and every inspection is carried out by NICEIC registered electricians. The new report arrives as a PDF by email. For anything else, contact us by phone.
020 3740 6785
Frequently Asked Questions
Does a C3 fail the report?
No. A C3 is a recommendation for improvement and does not on its own make the report unsatisfactory, so a report containing only C3 observations is satisfactory and no 28-day deadline applies. It is still worth noting what was recommended: items coded C3 now are often the ones that become C2 observations at a later inspection as the installation ages.
Do I need a new EICR after the remedial work?
Not under the regulations. What they require is written confirmation from a qualified and competent person that the work has been done and the standards are met, which you then give to tenants and the council. Some councils and licensing teams ask for a satisfactory EICR as well, and some landlords prefer one for their records, so a re-inspection can be arranged where it is wanted.
Can my tenant stay during the 28 days?
In most cases, yes. An unsatisfactory report does not of itself require the tenant to move out; it requires the landlord to have the work done within the period. Where a C1 is recorded, the danger must be dealt with straight away: the inspector will have told the occupant on the day which circuit to leave switched off at the consumer unit until a qualified electrician has attended.
Can I use any electrician for the remedial work?
The regulations require a qualified and competent person, which in practice means an electrician whose qualifications and experience cover the work and who can issue the certificate for it. You are free to choose who that is. The business can quote separately for the remedial work if you wish, and you can equally use another electrician and send us their confirmation at the next inspection.
Who tells the council?
The landlord does, but only where the council has asked for the report. The duty is to give the written confirmation to each tenant within 28 days of completion, and to the local authority within the same period where it requested the EICR. Councils that have not asked for the report do not need to be told, though they can ask at any time and must then receive a copy within 7 days.